Home › Home Remodeling Glossary › Change Order

Licensing and Contracts term

Change Order

Definition: A change order is the paperwork both you and your contractor sign mid project to put a revision in writing, spelling out which part of the job is changing and how that shifts the cost or the timeline.

What is a change order?

AIA Contract Documents describes a change order as a written agreement that changes the work, the contract sum, the contract time, or some combination. Once signed, it becomes one of the contract documents and binds the parties to the revised terms.

A change order does not always add cost. AIA notes it can also record deductive changes, credits, or a change with no adjustment to price or schedule at all.

Why it matters

Changes happen on almost every remodel: a different tile, an extra window, rot found behind old siding. A signed change order puts the new cost and timeline in writing before the work moves forward, so the final invoice matches what you agreed to and nobody is relying on a conversation from three weeks ago.

In Maryland, a written change order also affects cancellation rights. The MHIC explains that the Door-to-Door Sales Act does not apply to a transaction that results from a written change order agreed by buyer and seller under a contract they already signed, as long as the buyer gives a separate, dated statement in their own handwriting that describes the change and waives the right to cancel it.

Common reasons for change orders

AIA says mistakes are not the main cause. Most change orders come from:

  • Owner-requested scope changes during the project.
  • Unforeseen site conditions, such as concealed conditions or hazardous materials.
  • Delays beyond the parties’ control, such as shipping delays or severe weather.
  • Approved substitutions for specified products or methods.
  • Reconciliation of allowances and unit prices.

What a good change order shows

AIA’s advice is to write the change order for a reader who was not part of the original conversation. It should state:

  • What is changing.
  • Which contract documents are affected.
  • How the contract price is adjusted, if at all.
  • How the contract time is adjusted, if at all.
  • Each supporting attachment and its date.

AIA’s checklist also asks that the change be in writing, with no work going ahead on a verbal instruction alone.

Why the paperwork matters later

If a dispute reaches the Maryland Home Improvement Commission, its Guaranty Fund FAQ asks homeowners for copies of the contract, change orders and cancelled checks so an investigator can validate the claim. Claims that cannot be validated are dismissed without a hearing.

Learn more

These pages cover the license your contractor needs and the state fund that relies on your contract records.

Related Certified Home Remodelers services

Frequently asked questions

Does a change order always increase the price?

No. AIA Contract Documents notes a change order can record credits, deductive changes, or a change with no adjustment to price or time.

Can I cancel a change order under Maryland’s Door-to-Door Sales Act?

The MHIC says the Act does not apply to a written change order under a contract you already signed, if you give the seller a separate dated statement in your own handwriting that describes the change and waives the right to cancel.

Should work start before the change order is signed?

AIA’s checklist asks that the change be in writing and that no work proceed on a verbal instruction alone.

Sources

Planning a project in Carroll County?

Ask about your remodel, addition, roof or siding project: Contact Certified Home Remodelers.